Johnson Creek Covered Bridge Restoration Galleries

November 3, 2007

The work on the trusses has been completed, now the fabrication of the lower chord from new lumber is beginning. When that is completed and the flooring re-installed in the bridge, this will be the end of Phase 1 of the project. Phase 2 will begin when the funding is approved at an undetermined time in the future. Once Phase 2 begins, th ...

Updated: Nov 04, 2007 7:43am PST

September 1, 2007

The lower chord of the bridge, which had severely rotted, has been removed to facilitate the work on the truss. Currently each truss member is being removed, inspected and new wood is being spliced in with the old where needed. Although the lower chord had severely deteriorated over time and will be replaced with new wood, the rest of th ...

Updated: Sep 01, 2007 5:37pm PST

July 28, 2007

A temporary steel truss has been inserted into the bridge to support it during the renovation process. The weight of the bridge is now being totally supported by the steel truss and with the use of needle beams, the bridge has been raised off its abutments and pier. Once renovation is complete, the bridge will once again rest on its origi ...

Updated: Jul 28, 2007 6:29pm PST

May 27, 2007

Restoration will begin shortly! Arnold M. Graton & Associates are just getting established at the site. While browsing these photos, note the twisting and warping of the bridge. It is readily apparent when you see the "waving" of the floor on the interior shots. Return to KyCoveredBridges.org

Updated: May 27, 2007 4:18pm PST